Quantcast
Channel: Updates to NZ Transport Agency
Viewing all articles
Browse latest Browse all 3073

Construction Update

$
0
0

PROGRESS THROUGH SEPTEMBER

PROGRESS THROUGH AUGUST

Over the last month, work has involved pavement construction, bridge upgrades, service protections,locations, and various retaining walls.

The safe work zones are in place between Hill Road to Takanini Interchange:and the Pahurehure Inlet.

 

Hill Road to Takanini Interchange:

  • Base layers and asphaltAsphalt operations were laid to formcompleted in the new pavementmedian area between HillAlfriston Road and Alfriston Road.
  • Slip-form concrete barrier installation continued in the median.Takanini Interchange.
  • Earthworks and drainage continued along the southbound shoulder of the motorway. This included shaping of the new open channels (also known as swales), which help treat stormwater as it runs off the motorway.

Takanini Interchange to Pahurehure Inlet:

  • Earthworks and drainage installation were completed in the median and continued along the northboundsouthbound shoulder of the motorway. This included shaping of the new open channels (also known as swales),swales) which help treat stormwater as it runs off the motorway.
  • Asphalt operations commenced in the median.
  • Retaining wall and noise wall construction began on the southbound side of the motorway.
  • Installation of slip-form concrete barriers began in the median.

Other Areas: 

Takanini Interchange to Pahurehure Inlet:

  • Temporary guard railing was installed on the shoulder of the northbound motorway to create a safe work zone.

 

Other Areas:

  • On the Papakura Stream bridge,Bridge, just north of the railway line, ongoing substructure work and retaining wall construction continued.
  • Work continued to excavate and soil nail the abutments under bridges crossing the railway line and along the southbound off-ramp towards Spartan Road.
  • Work continued on the placement of precast retaining wall panels nearestand the reinforcing cage for the northern abutment of the Spartan Road Bridge.
  • Continued offsite precasting components for retaining walls, noise walls, and bridges.

 

WORK BEING UNDERTAKEN IN OCTOBER

WORK BEING UNDERTAKEN IN SEPTEMBER

Over the next month, we will continue working in the median and shoulders between Hill Road and the Pahurehure Inlet. We will also continue working to widen the motorway bridges over the Papakura StreamStream, and the KiwiRail Lines. WeLines. Service investigations will utilise opportunities tocontinue for future work on the northbound side of the motorway, however, our focus remains on the southbound side. This will ensure we achieve our goal of an additional lane from Hill Roadareas to north of the Pahurehure Inlet (excluding the Takanini Interchange) by the end of March 2017.be established, including works around major utilities such as gas, water, and power main lines. Work this month includes:

 

Hill Road to Takanini Interchange:

  • In the median, base layers will be laid to form the new pavement between Hill Road toand Alfriston Road:

    • Road.
    • Installation of lighting structuresAsphalt operations will commence in the median barrier.between Hill Road and Alfriston Road.
    • Temporary pavement operationsInstallation of slip-form concrete barriers will continue in the median under Alfriston Bridgemedian.
    • Earthworks and drainage installation will continue along the southbound shoulder of the motorway. This includes shaping of the new open channels (also known as swales) which help treat stormwater as it runs off the motorway.
    • Earthworks and drainage will continue along the southbound shoulder of the motorway and under the Alfriston Bridge. This includes shaping of the new open channels (also known as swales), which help treat stormwater as it runs off the motorway.

    Alfriston Road to Takanini Interchange:

    • Installation of lighting structures in the median barrier.
    • Earthworks and drainage will continue along the southbound shoulder of the motorway. This includes shaping of the new open channels (also known as swales), which help treat stormwater as it runs off the motorway.
    • Retaining wall construction will commence along the southbound side of the motorway.

    Takanini Interchange to Pahurehure Inlet: 

    Takanini Interchange to Pahurehure Inlet:

    • Asphalt operations will continuebegin in the median betweenmedian between the Takanini Interchange and Walter Strevens Drive.the Pahurehure Inlet.
    • Installation of slip-form concrete barriers will continue in the median.
    • Vegetation clearance continuesremoval and mulching will continue on the shoulder along the southbound shoulder in preparation for retaining wall and noise wall construction.northbound side of the motorway.
    • Retaining wall and noise wall construction will commence on the southbound side of the motorway.
    • Earthworks and drainage will continue alonginstallation commence on the northbound and southbound shouldersshoulder of the motorway. This includesincluded shaping of the new open channels (also known as swales),swales) which help treat stormwater as it runs off the motorway.
    • On the southbound side of the motorway, retaining wall and noise wall construction will commence.

    Other Areas: 

    Other Areas:

    • On the Papakura Stream bridge, beam installation will commence, and substructuresubstructure work and retaining wall construction will continue. is ongoing.
    • On the Spartan Road Bridge, beam installation will commence, and work willWe continue on the placement of precast retaining wall panels.
    • Continued offsite precasting components for noise walls, retaining walls, noise walls, and bridges.
    • Work continues on the placement of precast retaining wall panels nearest the Spartan Road Bridge.
    • Across the project, long term environmental controls are being installed to maintain water quality during construction.

     

    With the lanes narrowed, there is less time to react to other vehicles and  itIt is important that motorists keep to the 80 km/h speed limit past our work areas. There will be ongoing truck and project vehicle movements accessing the shoulder and the median work sites. Keeping both motorists and our team members as safe as possible is imperative and we need everyone's help to do this.

    As always, we will be doing our best to minimise effects of these works on motorists as much as we can. We thank you for your patience as we work to improve journey reliability and safety along the Southern Corridor.

     


Viewing all articles
Browse latest Browse all 3073

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>