The NZ Transport Agency’s Fulton Hogan team will replace existing running planks with new 50mm planks, fully upgrade steel angle connections and reseal the deck.
- Hour Hou Creek map
http://www.topomap.co.nz/NZTopoMap/nz31832/Houhou-Creek/West-Coast
Traffic management
Stop and go manual traffic management will be needed for some of the work with some delays when the bridge deck is being replaced. Short delays of up to five minutes may occur in the first couple of weeks. Longer delays will not begin until later in November.
Electronic message boards will advertise delays for drivers so people know what to expect and the local dairy company and transport businesses will be kept informed.